2022 Capital Projects
Community Services & Facilities - FlightExec Centre
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
FlightExec Centre Security Measures Upgrade some existing security cameras with reduced image clarity March 2202 May 2202 In Progress Devon Brown
FlightExec Centre Engineer Study Investigate storm water management concerns in north parking lot and with drainage above/around gymnasium TBD TBD Not Active Steve MacDonald
FlightExec Centre SWM Remediation Address storm water management concerns above/around gymnasium based on results from engineer study March 2022 TBD Creating tender document Steve MacDonald
FlightExec Centre Dehumidifier Repair dehumidifier for arena ice surfaces, which will prolong useful life of this unit. February 2022 April 2022 Parts on Order Devon Brown
FlightExec Centre Hot Water Tank Replace hot water storage tanks in flooder room, end of useful life January 2022 January 2022 Complete Devon Brown
Community Services & Facilities - Parks and Trails

PROJECT NAME

SCOPE

ANTICIPATED START DATE

ANTICIPATED COMPLETION DATE

STATUS

PROJECT CONTACT

Accessible Playground Build an accessible/inclusive playground at Dorchester Park January 2022 July 2022 Equipment on Order Steve MacDonald
Phase 2 - Walking Path Lights Install second (and final) phase of walking path lights at Dorchester Park Sept 2021 May 2022 Parts on back order Devon Brown
Thorndale Dog Park Build dog park in Thorndale April 2022 TBD Forming Committee Steve MacDonald

Parking Lot

Build gravel parking lot beside Agnes St. road extension at Thorndale Park February 2022 TBD Pricing Materials Devon Brown

Entrance Laneway

Create new entrance to Crampton Park from Crampton Drive once surplus portion of land adjacent to this park is sold TBD TBD Pending sale of surplus land Devon Brown

Annual Fencing Budget

2022 fencing maintenance will include work at Thorndale Park and at ORC for parking and four ball concerns at soccer pitch #5 March 2022 TBD In Progresss Devon Brown

Annual Playground Budget

Install new playground at Crampton Park, with balance to budget to address any required repairs at all locations TBD TBD Not Active Devon Brown
Ec. Dev Festive Lights Purchase festive light displays to hang on walking path lights at Dorchester Park TBD TBD Not Active Devon Brown
Annual Trails Budget Includes maintenance/upgrades to Thorndale Park and Mill Pond Trails TBD TBD Not Active Devon Brown
Trails Mill Pond Crib Walls Repairs and replacement of various crib walls at Mill Pond trails due to erosion April 2022 July 2022 Set to Start Devon Brown
Community Services & Facilities - Sport Fields
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
Ball Diamonds Artificial Turf Diamond Build new/second ball diamond at the Outdoor Recreation Complex, with artificial turf January 2022 Summer 2022 Various items on order, breaking ground late March Steve MacDonald
Ball Diamonds Dorchester Infield Upgrade Convert infield for diamonds #3 and #4 at Dorchester Park to clay March 2022 April 2022 Planning/Scheduling Devon Brown
Ball Diamonds Thorndale Infield Upgrade Convert infield for diamonds #3 at Thorndale Park to clay March 2022 April 2022 Planning/Scheduling Devon Brown
Ball Diamonds ORC Security Measures Install security system at Outdoor Recreation Complex TBD TBD Not Active Devon Brown
ORC Soccer Covered Benches Install covered benches for full size soccer pitch at the Outdoor Recreation Complex February 2022 April 2022 On Order Devon Brown
Community Services & Facilities - Thorndale Lions Community Centre
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
Thorndale Lions CC - Fire & Security Measures Install fire monitoring and security system for this new facility March 2022 April 2022 In Progress Devon Brown
Thorndale Lions CC Display Cases Display cases for meeting room #3, to provide space to exhibit community-related items. Jan 2022 April 2022 On Order Steve MacDonald
Thorndale Lions CC Various Window tinting for meeting rooms, plumbing for floor scrubber, small kitchen wares. Jan 2022 April 2022 Complete except for Kitchen wares, on order Devon Brown
Thorndale Fieldhouse Security Measures Install security camera in response to ongoing vandalism at this new facility January 2022 April 2022 Components on order Devon Brown
Community Services & Facilities - Other (Municipal Office, Senior Centre, Dorchester Library & Cemetery)

PROJECT NAME

SCOPE

ANTICIPATED START DATE

ANTICIPATED COMPLETION DATE

STATUS

PROJECT CONTACT

Senior Centre Architectural/ Engineering Plans Production of architectural and engineering plans and technical documents which will then be used to solicit bids for addition to Senior Centre in 2023 March 2022 September 2022 Creating bid document Steve MacDonald
Municipal Office Parking Lot Re-pave and add curbs to parking lot once underground is completed in relation to upcoming work at neighbouring school TBD TBD Pending completion of other site work Steve MacDonald
Municipal Office EV Charging Station Install duo electronic vehicle charging station for municipal office parking lot in conjunction with the paving project TBD TBD Pending completion of other site work Steve MacDonald
Dorchester Library Roof Replacement Replace peaked and flat roof January TBD In Progress Devon Brown
Dorchester Cemetery Columbarium New columbarium for south cremation garden March TBD In Progress Devon Brown
Public Works - Construction Projects
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
King Street - Sanitary Sewer Construction Finalizing 2021 construction restoration in 2022 Ongoing March 2022 Completed Tanner Stanton
Porter Subdivision Reconstruction - Phase 1 Storm, WM, Roads, Curb and Sidewalks July 2022 December 2022 Finalizing Construction Tanner Stanton
Hamilton Road/Oakwood Drive Sanitary Trunk Sewer Installation Sanitary, Roads, Curb and Sidewalks July 2022 December 2022 Ongoing Tanner Stanton
Oakwood Place Reconstruction Storm, Sanitary, WM, Roads, Curb July 2022 December 2022 Ongoing Tanner Stanton
Fairview Road Bridge #26 - Repairs and Rehabilitation Bridge Deck Repairs, Installation of Barriers June 2022 August 2022 Complete Jake McKillop
Minnie Street - Realignment of CN Track Approaches Road & Sidewalk - Grade realignment of approaches to CN tracks TBD TBD TBD Tanner Stanton
Byron Ave Resurfacing Mill and resurface top coat of asphalt TBD TBD Complete Jake McKillop
Park Lane & Countryside Lane - Resurface & SW Repairs Shave and pave, sidewalk panel replacements TBD TBD Complete Jake McKillop
Heritage Road, Thompson Drive, Purple Hill Road - Gravel Upgrades Gravel road upgrades July 2022 August 2022 Complete Jake McKillop
North Street Resurfacing Shave and pave May 2022 August 2022 Complete Jake McKillop
Thorndale South Trunk Watermain - Foxborough Subdivision Watermain installation TBD TBD Deferred Kevin Willson
Landfill Pond - Sediment Removal Removal of suspended solids 2022 2022 Complete Kevin Willson
Dorchester Water Treatment Baffle Replacement Drinking water storage repairs TBD TBD Deferred Kevin Willson
Thorndale Well #2 Pump New pump to allow for higher flow rates in Thorndale 2022 2022 Complete Kevin Willson
Dorchester Shallow Wells Supply Expansion Increase well supply capacity Ongoing TBD Ongoing Kevin Willson
Dorchester Water Storage Mixers THM reduction program TBD TBD Not Active Kevin Willson
Public Works - Design & Investigative Projects
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
Thorndale Industrial Park Watermain Looping Design Thorndale industrial park watermain 300mm looping design TBD TBD Deferred Kevin Willson
Watermain South CN/Rosewood Crossing 300mm 300mm Watermain South CN/ Rosewood Crossing TBD TBD Deferred Kevin Willson
Dale Drive Watermain Replacement Watermain Replacement 2022 2022 Complete Kevin Willson
Wastewater Design - North on Mill to Christie & Westerly to Wheeler 300mm watermain design - North on Mill to Christie & Westerly to Wheeler TBD TBD Deferred Kevin Willson
Dorchester Groundwater Management Supply Increase well supply capacity Ongoing 2023 Active Kevin Willson
Minnie Street Watermain Replacement Watermain Replacement 2022 2022 Complete Kevin Willson
Thorndale WTP EA Study Future expansion/replacement for Thorndale WTF Spring 2022 2023 Active Kevin Willson
Public Works - Fleet Services Projects
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
2002 963C Cat Crawler/ Loader Replacement Replacement Unit 2022 2022 Complete Kevin Willson
2010 New Holland Tractor Replacement Replacement Unit 2021 2022 Complete Jake McKillop
2013 John Deere Tractor Backhoe Replacement Replacement Unit 2022 2023 Anticipating Jan 2023 Tender Jake McKillop
New 1/2 ton pick up truck for Recreation Department New Truck Addition 2022 2022 Complete Jake McKillop
New Water Tank for Construction Activities Replacement Unit 2022 2023 Ongoing Jake McKillop
Front Plow and Rear Salter Unit Replacement Unit 2022 2022 Complete Devon Brown
New Tandem Plow Truck Replacement Unit Ongoing March 2022 Ordered - Waiting for Delivery Jake McKillop

 

 

2023 Capital Projects - as of January 18, 2023
Public Works - Construction Projects
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
Porter Subdivision Reconstruction - Phase 1 Storm, WM, Roads, Curb and Sidewalks Apr 2023 May 2023 Active - Finalizing Construction Tanner Stanton
Porters Subdivision Watermain Replacement - Phase 2 Watermain, Storm, Curb and Sidewalks May 2023 November 2023 Active - Finalizing Tender Tanner Stanton
Hamilton Road/ Oakwood Drive Sanitary Trunk Sewer Installation Sanitary, Roads, Curb and Sidwalks March 2023 May 2023 Active - Finalizing Construction Tanner Stanton
Oakwood Place Reconstruction Storm, Sanitary,  WM, Roads, Curb March 2023 May 2023 Active - Finalizing Construction Tanner Stanton
Woodvale Drive Sanitary Sewer Repair Replacing settled Sanitary Sewer Pipe March 2023 June 2023 Active - Tender Preparation Tanner Stanton
Bridge and Culvert Work (Bridge #26) Waterproofing Deck, asphalt. (Culver #132) Replacement June 2023 August 2023 Ongoing Jake McKillop
Minnie Street - Realignment of CN track approaches Road & Sidewalk- Grade Realignment of approaches to CN Tracks TBD TBD Active Tanner Stanton
Traffic Counter Purchasing Traffic Counters to update classification of roads January 2023 April 2023 Soliciting Quotes Jake McKillop
Thorndale South Trunk Watermain - Foxborough Subdivision Watermain Installation TBD TBD Deferred Kevin Willson
Dorchester Water Treatment Baffle Replacement Drinking water storage repair TBD TBD Active Kevin Willson
Thorndale EST - Interior and exterior Tank Cleaning Cleaning and inspection of Thorndale Elevated Storage Tank 2023 2023 Active Kevin Willson
Dorchester Water Plant HLP-1 rebuild Replacing internal components of High Lift Pump #1 2023 2023 Active Kevin Willson
Dorchester Shallow Wells Supply Expansion Increase well suppy capacity Ongoing TBD Ongoing Kevin Willson
Dorchester Water Storage Mixers THM reduction program TBD TBD Active Kevin Willson
Public Works - Design & Investigative Projects
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
Thorndale Industrial Park Watermain Looping Design Thorndale Industrial Park Watermain 300mm Looping Design TBD TBD Deferred Kevin Willson
Watermain South CN/ Rosewood Crossing 300mm  300mm Watermain South CN/ Rosewood Crossing TBD TBD Deferred Kevin Willson
Dorchester Groundwater Management Supply Increase well supply capacity ongoing 2023 Active Kevin Willson
Thorndale WTP EA Study Future expansion/replacement for Thorndale WTF 2023 2023 Active Kevin Willson
Thorndale WWTP - Class EA Class EA for a Thorndale WWTP Expansion 2023 2026 TBD Kevin Willson
Porters Subdivision Watermain Replacement - Phase 3 Replacement of Watermain from Carl Street to St. Davids Public School 2023 2023 Active Tanner Stanton
Dorchester WTF - UV system upgrade design and treatment optimization (THM/ HAA Reduction) Study to include design/ replacement of UV disinfection system as well as treatment option to reduce THM/HAA's 2023 2023 Active Kevin Willson
Public Works - Fleet Services
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
Zero Turn Lawn Mower Replacement Replacement Unit 2023 2023 Soliciting Quotes Devon Brown
Fire Department Rescue Truck Replacement Replacement Unit 2023 2023 Active - Tender Preparation Colin Shewell
Water Tank  Replacement Unit 2023 2023 Soliciting Quotes Jake McKillop
Community Services & Facilities - FlightExec Centre
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
Expansion Project - Senior Centre, VON & Auditorium Renovation/addition to Senior Centre and VON, with upgrades to Auditorium. 2022 Spring 2024 In Progress Steve MacDonald
Wireless Access Point Replacement Replace/upgrade W.A.P. to improve WiFi signal strength. Feb 2023 Spring 2023 Not Started Devon Brown
Engineer Study - SWM - Gym & Parking Lot Assess existing storm water mgmt including potential leak/flood risks. Spring 2023 Summer 2023 Not Started Steve MacDonald
SWM - Remediation for Gym & Parking Lot Address any issues from engineer study to eliminate floods risks. Summer 2023 Fall 2023 Not Started Steve MacDonald
Engineer Study - 3 SWM drains - North Parking Lot Design, engineer and contract work to address 3 storm water drain pipes. Spring 2023 Fall 2023 Not Started Steve MacDonald
Dehumidifier Repair Replace AHU burner (burner, motor & blower) and further diagnostics & training. January 2023 Spring 2023 In Progress Devon Brown
Security Cameras Upgrades Continued replacement of aging cameras that are no longer performing optimally. February 2023 Summer 2023 Not Started Devon Brown
Repairs to Roof over Flooder Room and DR #8 Repairs/restoration to this leaking roof portion which will extend useful life. February 2023 Summer 2023 Not Started Devon Brown
Community Services & Facilities - Thorndale Lions Community Centre
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
Internet/Wifi Improvements Additional hardware to improve connectivity. January 2023 Spring 2023 In Progress Devon Brown
Lobby Monitor 50" monitor for lobby, will display bookings, etc. February 2023 April 2023 Not Started Devon Brown
Security Cameras  Install video security system at our newest facility. January 2023 April 2023 In Progress Devon Brown
Community Services & Facilities - Parks & Trails
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
Connectivity and laptop for Aquatics Staff. Enable aquatics staff to access internet and department software from pool building. Spring 2023 Spring 2023 Not Started Devon Brown
ORC Security Security measures in response to vandalism issues at this facility. 2022 Spring 2023 In Progress Devon Brown
Thorndale Dog Park Dog park being created for Thorndale. 2022 Summer 2023 In Progress Steve MacDonald
Fencing - Various Annual repairs, maintenance and additions to fencing at our parks, trails & facilities. Spring 2023 Fall 2023 Not Started Devon Brown
Playground - Various  Annual improvements and replacements, will include addition to Crampton Park. January 2023 Summer 2023 In Progress Devon Brown
Thorndale Park - Sidewalk Extension New sidewalk from poultry building to playground. January 2023 Spring 2023 In Progress Devon Brown
Trails - Various 2023 to include extension to railway trail and continued repairs to crib walls at Mill Pond trail. Spring 2023 Fall 2023 Not Started Devon Brown
Catherine St. Predestrian Bridge Replace aging pedestrian bridge. Spring 2023 Summer 2023 Not Started Devon Brown
Community Services & Facilities - Sports Fields
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
Artificial Turf Maintenance Equipment Pull-behind groomer and manual tools to maintain the artificial turf. February 2023 April 2023 Not Started Devon Brown
           
Community Services & Facilities - Other (Fleet, Municipal Office, Cemetery)
PROJECT NAME SCOPE ANTICIPATED START DATE ANTICIPATED COMPLETION DATE STATUS PROJECT CONTACT
Zero-Turn Lawn Mower Replacement of Unit #5 January 2023 March 2023 In Progress Devon Brown
Municipal Office - Building Condition & Risk Assessment Conduct building condition assessment and risk assessment on facility. February 2023 June 2023 Not Started Steve MacDonald
Municipal Office - Site Work Engineer, design and construction including - paving, curbs, SWM, water service, sanitary and more. February 2023 Summer 2023 In Progress Steve MacDonald
Municipal Office - E.V. Charging Station Install EV charging station for office visitors, as part of larger site work project. February 2023 Summer 2023 Not Started Steve MacDonald
Dorchester Union Cemetery - Cement Cement pad and concrete brick barriers for maintenance area. January 2023 Spring 2023 In Progress Devon Brown