Community Services & Facilities - FlightExec Centre
PROJECT NAME | SCOPE | ANTICIPATED START DATE | ANTICIPATED COMPLETION DATE | STATUS | PROJECT CONTACT |
FlightExec Centre Security Measures | Upgrade some existing security cameras with reduced image clarity | March 2202 | May 2202 | In Progress | Devon Brown |
FlightExec Centre Engineer Study | Investigate storm water management concerns in north parking lot and with drainage above/around gymnasium | TBD | TBD | Not Active | Steve MacDonald |
FlightExec Centre SWM Remediation | Address storm water management concerns above/around gymnasium based on results from engineer study | March 2022 | TBD | Creating tender document | Steve MacDonald |
FlightExec Centre Dehumidifier | Repair dehumidifier for arena ice surfaces, which will prolong useful life of this unit. | February 2022 | April 2022 | Parts on Order | Devon Brown |
Community Services & Facilities - Parks and Trails
PROJECT NAME |
SCOPE |
ANTICIPATED START DATE |
ANTICIPATED COMPLETION DATE |
STATUS |
PROJECT CONTACT |
Accessible Playground | Build an accessible/inclusive playground at Dorchester Park | January 2022 | July 2022 | Equipment on Order | Steve MacDonald |
Phase 2 - Walking Path Lights | Install second (and final) phase of walking path lights at Dorchester Park | Sept 2021 | May 2022 | Parts on back order | Devon Brown |
Thorndale Dog Park | Build dog park in Thorndale | April 2022 | TBD | Forming Committee | Steve MacDonald |
Parking Lot |
Build gravel parking lot beside Agnes St. road extension at Thorndale Park | February 2022 | TBD | Pricing Materials | Devon Brown |
Entrance Laneway |
Create new entrance to Crampton Park from Crampton Drive once surplus portion of land adjacent to this park is sold | TBD | TBD | Pending sale of surplus land | Devon Brown |
Annual Fencing Budget |
2022 fencing maintenance will include work at Thorndale Park and at ORC for parking and four ball concerns at soccer pitch #5 | March 2022 | TBD | In Progresss | Devon Brown |
Annual Playground Budget |
Install new playground at Crampton Park, with balance to budget to address any required repairs at all locations | TBD | TBD | Not Active | Devon Brown |
Ec. Dev Festive Lights | Purchase festive light displays to hang on walking path lights at Dorchester Park | TBD | TBD | Not Active | Devon Brown |
Annual Trails Budget | Includes maintenance/upgrades to Thorndale Park and Mill Pond Trails | TBD | TBD | Not Active | Devon Brown |
Trails Mill Pond Crib Walls | Repairs and replacement of various crib walls at Mill Pond trails due to erosion | April 2022 | July 2022 | Set to Start | Devon Brown |
Community Services & Facilities - Sport Fields
PROJECT NAME | SCOPE | ANTICIPATED START DATE | ANTICIPATED COMPLETION DATE | STATUS | PROJECT CONTACT |
Ball Diamonds Artificial Turf Diamond | Build new/second ball diamond at the Outdoor Recreation Complex, with artificial turf | January 2022 | Summer 2022 | Various items on order, breaking ground late March | Steve MacDonald |
Ball Diamonds Dorchester Infield Upgrade | Convert infield for diamonds #3 and #4 at Dorchester Park to clay | March 2022 | April 2022 | Planning/Scheduling | Devon Brown |
Ball Diamonds Thorndale Infield Upgrade | Convert infield for diamonds #3 at Thorndale Park to clay | March 2022 | April 2022 | Planning/Scheduling | Devon Brown |
Ball Diamonds ORC Security Measures | Install security system at Outdoor Recreation Complex | TBD | TBD | Not Active | Devon Brown |
ORC Soccer Covered Benches | Install covered benches for full size soccer pitch at the Outdoor Recreation Complex | February 2022 | April 2022 | On Order | Devon Brown |
Community Services & Facilities - Thorndale Lions Community Centre
PROJECT NAME | SCOPE | ANTICIPATED START DATE | ANTICIPATED COMPLETION DATE | STATUS | PROJECT CONTACT |
Thorndale Lions CC - Fire & Security Measures | Install fire monitoring and security system for this new facility | March 2022 | April 2022 | In Progress | Devon Brown |
Thorndale Lions CC Display Cases | Display cases for meeting room #3, to provide space to exhibit community-related items. | Jan 2022 | April 2022 | On Order | Steve MacDonald |
Thorndale Lions CC Various | Window tinting for meeting rooms, plumbing for floor scrubber, small kitchen wares. | Jan 2022 | April 2022 | Complete except for Kitchen wares, on order | Devon Brown |
Thorndale Fieldhouse Security Measures | Install security camera in response to ongoing vandalism at this new facility | January 2022 | April 2022 | Components on order | Devon Brown |
Community Services & Facilities - Other (Municipal Office, Senior Centre, Dorchester Library & Cemetery)
PROJECT NAME |
SCOPE |
ANTICIPATED START DATE |
ANTICIPATED COMPLETION DATE |
STATUS |
PROJECT CONTACT |
Senior Centre Architectural/ Engineering Plans | Production of architectural and engineering plans and technical documents which will then be used to solicit bids for addition to Senior Centre in 2023 | March 2022 | September 2022 | Creating bid document | Steve MacDonald |
Municipal Office Parking Lot | Re-pave and add curbs to parking lot once underground is completed in relation to upcoming work at neighbouring school | TBD | TBD | Pending completion of other site work | Steve MacDonald |
Municipal Office EV Charging Station | Install duo electronic vehicle charging station for municipal office parking lot in conjunction with the paving project | TBD | TBD | Pending completion of other site work | Steve MacDonald |
Dorchester Library Roof Replacement | Replace peaked and flat roof | January | TBD | In Progress | Devon Brown |
Dorchester Cemetery Columbarium | New columbarium for south cremation garden | March | TBD | In Progress | Devon Brown |
Public Works - Construction Projects
PROJECT NAME | SCOPE | ANTICIPATED START DATE | ANTICIPATED COMPLETION DATE | STATUS | PROJECT CONTACT |
King Street - Sanitary Sewer Construction | Finalizing 2021 construction restoration in 2022 | Ongoing | March 2022 | Active | Tanner Stanton |
Porter Subdivision Reconstruction - Phase 1 | Storm, WM, Roads, Curb and Sidewalks | July 2022 | December 2022 | Active - Finalizing Tender | Tanner Stanton |
Hamilton Road/Oakwood Drive Sanitary Trunk Sewer Installation | Sanitary, Roads, Curb and Sidewalks | July 2022 | December 2022 | Active - Design Phase | Tanner Stanton |
Oakwood Place Reconstruction | Storm, Sanitary, WM, Roads, Curb | July 2022 | December 2022 | Active - Design Phase | Tanner Stanton |
Fairview Road Bridge #26 - Repairs and Rehabilitation | Bridge Deck Repairs, Installation of Barriers | June 2022 | August 2022 | Not Active | Jake McKillop |
Minnie Street - Realignment of CN Track Approaches | Road & Sidewalk - Grade realignment of approaches to CN tracks | TBD | TBD | Active - Design Work Complete | Tanner Stanton |
Byron Ave Resurfacing | Mill and resurface top coat of asphalt | TBD | TBD | Active - Tender Preparation | Jake McKillop |
Park Lane & Countryside Lane - Resurface & SW Repairs | Shave and pave, sidewalk panel replacements | TBD | TBD | Active - Tender Preparation | Jake McKillop |
Heritage Road, Thompson Drive, Purple Hill Road - Gravel Upgrades | Gravel road upgrades | July 2022 | August 2022 | Active - Tender Preparation | Jake McKillop |
North Street Resurfacing | Shave and pave | May 2022 | August 2022 | Active - Tender Preparation | Jake McKillop |
Thorndale South Trunk Watermain - Foxborough Subdivision | Watermain installation | TBD | TBD | Not Active | Kevin Willson |
Landfill Pond - Sediment Removal | Removal of suspended solids | TBD | TBD | Not Active | Kevin Willson |
Dorchester Water Treatment Baffle Replacement | Drinking water storage repairs | Spring 2022 | Spring 2022 | Active | Kevin Willson |
Thorndale Well #2 Pump | New pump to allow for higher flow rates in Thorndale | Spring 2022 | Summer 2022 | Active | Kevin Willson |
Dorchester Shallow Wells Supply Expansion | Increase well supply capacity | Ongoing | Fall 2022 | Ongoing | Kevin Willson |
Dorchester Water Storage Mixers | THM reduction program | TBD | TBD | Not Active | Kevin Willson |
Public Works - Design & Investigative Projects
PROJECT NAME | SCOPE | ANTICIPATED START DATE | ANTICIPATED COMPLETION DATE | STATUS | PROJECT CONTACT |
Thorndale Industrial Park Watermain Looping Design | Thorndale industrial park watermain 300mm looping design | TBD | TBD | Active | Kevin Willson |
Watermain South CN/Rosewood Crossing 300mm | 300mm Watermain South CN/ Rosewood Crossing | TBD | TBD | Active | Kevin Willson |
Dale Drive Watermain Replacement | Watermain Replacement | On hold | On hold | Design Work Complete | Kevin Willson |
Wastewater Design - North on Mill to Christie & Westerly to Wheeler | 300mm watermain design - North on Mill to Christie & Westerly to Wheeler | TBD | TBD | Active | Kevin Willson |
Dorchester Groundwater Management Supply | Increase well supply capacity | Ongoing | Fall 2022 | Active | Kevin Willson |
Minnie Street Watermain Replacement | Watermain Replacement | On hold | On hold | Design Work Complete | Kevin Willson |
Thorndale WTP EA Study | Future expansion/replacement for Thorndale WTF | Spring 2022 | 2022 | Active | Kevin Willson |
Public Works - Fleet Services Projects
PROJECT NAME | SCOPE | ANTICIPATED START DATE | ANTICIPATED COMPLETION DATE | STATUS | PROJECT CONTACT |
2002 963C Cat Crawler/ Loader Replacement | Replacement Unit | 2022 | 2022 | Complete | Kevin Willson |
2010 New Holland Tractor Replacement | Replacement Unit | 2021 | 2022 | Complete | Jake McKillop |
2013 John Deere Tractor Backhoe Replacement | Replacement Unit | 2022 | 2022 | Active - Tender Closed | Jake McKillop |
New 1/2 ton pick up truck for Recreation Department | New Truck Addition | 2022 | 2022 | Complete | Jake McKillop |
Front Plow and Rear Salter Unit | Replacement Unit | 2022 | 2022 | Complete | Devon Brown |
New Tandem Plow Truck | Replacement Unit | Ongoing | March 2022 | Ordered - Waiting for Delivery | Jake McKillop |